Chapter 1 · Lesson 1.3
The four pillars of the policy and the hazard study
French industrial risk policy rests on four complementary pillars, with the hazard study as their foundation.
The four pillars
1. Risk reduction at source
Controlling dangerous installations: products, equipment, processes. The aim is to reduce the hazard and control risks where they originate.
2. Emergency plans
On-site emergency plan (POI, under the operator’s responsibility) and off-site emergency plan (PPI, under the authority of the prefect).
3. Public information
Informing and explaining to potential targets (neighbours, populations, nearby businesses).
4. Control of urban development
Choosing how to develop land around a site (technological risk prevention plans, PPRT).
Around a hazardous installation, we thus distinguish the source (products, equipment), the flow (propagation) and the receptors (human beings, environment, infrastructure). Reducing the hazard and controlling risks act on the source; urban planning and emergency plans act on the receptors.
The hazard study, at the heart of the system
Hazard studies, required by the order of 26 May 2014 (which replaced that of 10 May 2000) in application of the Seveso Directive, like those required by the law of 19 July 1976 on classified installations, aim to:
- identify the sources of hazard;
- specify the means used to prevent accidents or limit their consequences (prevention measures);
- analyse scenarios by quantifying their effects, even those of very low probability but large magnitude.
A scenario is a succession of linked events, from the initial aggression or failure to the assessment of the final consequences. Prevention measures aim to reduce the probability of accidents, reduce their possible effects and improve the safety of the installation.
What is the hazard study for?
- Determine the risk control measures (pillar 1);
- choose how to develop land around a site (pillar 4);
- define the actions to take in case of an accident (pillar 2);
- inform and explain to potential targets (pillar 3).
Four pillars: reduction at source, emergency plans, public information, control of urban development. The hazard study feeds all four: it identifies hazards, analyses scenarios and quantifies their effects, including for very unlikely accidents.