Chapter 1 · Lesson 1.1
Why and when to analyse the risks of an installation
A technical risk analysis describes how an installation can go wrong, with what consequences, and what already prevents it.
At design stage
The most cost-effective moment: a hazard removed on the drawing board costs almost nothing.
On an existing installation
Review of the current state, modification, lessons learned after an incident, regulatory safety report.
Before start-up
Safety review of commissioning, procedures and barriers.
Vocabulary
- Hazard source : energy, product, moving part or pressurised element.
- Hazardous situation : hazard source + initiating event (fault, deviation).
- Top event (TE): the loss of control (leak, rupture, fire outbreak).
- Hazardous phenomenon and target : the effect (fire, explosion, toxic release) and what it reaches (people, installation, environment).
- Barrier : what reduces the probability (prevention) or the severity (protection).
Prevention and protection
Before the TE, we reduce the probability; afterwards, we reduce the consequences. A complete analysis looks at both.
Source: “Industrial risks” course (chapters 1 to 3).