Chapter 1 · Lesson 1.4
The risk management process
The process is the “method” part of the standard: six iterative elements that apply to an activity, an installation, a project or the whole organisation.
Updated: October 2026. Sources: text of ISO 31000:2018, clause 6.
The elements of the process (clause 6)
| Element | Purpose (in substance) | Where to see it |
|---|---|---|
| 6.2 Communication and consultation | Help stakeholders understand risk, the basis of decisions and the reasons for actions; throughout the process. | Safety Report, chapter 2 (PPRT); lesson 1-8 |
| 6.3 Scope, context and criteria | Customise the process: define the scope, understand the external and internal contexts, set the risk criteria. | lesson 1-5 |
| 6.4 Risk assessment | Identify, analyse, evaluate. | lesson 1-6; Safety Report, chapters 3 and 4 |
| 6.5 Risk treatment | Select and implement options, verify their effectiveness, decide whether the residual risk is acceptable. | lesson 1-7; Industrial Risks 2, chapter 1 |
| 6.6 Monitoring and review | Assure and improve the quality and effectiveness of design, implementation and outcomes; at all stages. | lesson 1-8 |
| 6.7 Recording and reporting | Document and report the process and its outcomes for decision making, improvement and dialogue with stakeholders. | lesson 1-8; Safety Report, chapter 1 |
The standard states that the process is “often presented as sequential” but is iterative in practice, and that the variable nature of human behaviour and culture must be taken into account at all stages.
Communication and consultation
- Communicating, is sharing information about risk; consulting, is gathering views and information to inform the decision. Both bring together different expertise and win the support of those who bear the risk.
- On site : team meetings, safety briefings, group analyses, staff bodies. Externally : site monitoring committee, public PPRT meetings, information for residents.
Perception and acceptability
Judgement about risk rests on each person’s perception, which can weigh on decisions: a risk judged “acceptable” by the operator may not be so for residents. Consultation serves to make known what is acceptable and why.
Running example: the process applied to Val-des-Pins
- Context and criteria : upper-tier Seveso depot (assumption), inhabited surroundings, regulatory and internal criteria (lesson 1-5).
- Identification : PHA then HAZOP by line: tank BLEVE, leak at the loading point, overfilling (Safety Report course, chapter 3).
- Analysis : probability, intensity, severity (Safety Report course, chapter 4), barrier reliability (Industrial Risks 2 course, chapter 1).
- Assessment : compare with the matrix and the tolerated gap (Industrial Risks 2 course, LOPA).
- Treatment : add an SIS, a fail-safe valve, an earth mound, reduce the inventory (lesson 1-7).
- Monitoring : periodic tests, indicators, audits, lessons learned (lesson 1-8). Recording : safety report, risk register, management reports.