Chapter 1 · Lesson 1.4

The risk management process

The process is the “method” part of the standard: six iterative elements that apply to an activity, an installation, a project or the whole organisation.

Updated: October 2026. Sources: text of ISO 31000:2018, clause 6.

Risk management process (ISO 31000:2018)An iterative process. Two vertical bars accompany every step: on the left communication and consultation, on the right monitoring and review. In the centre, from top to bottom: scope, context and criteria; risk assessment, which comprises identification, analysis and evaluation; risk treatment. At the bottom, across the full width, recording and reporting.Communication and consultationMonitoring and reviewScope, contextand criteriaRISK ASSESSMENTIdentificationAnalysisAssessmentRisk treatmentTreatment feeds back into assessment:is the residual risk acceptable?Recording and reporting
The process is presented sequentially, but it is iterative: each step can call earlier ones into question. Diagram redrawn from the structure of the standard.

The elements of the process (clause 6)

ElementPurpose (in substance)Where to see it
6.2 Communication and consultationHelp stakeholders understand risk, the basis of decisions and the reasons for actions; throughout the process.Safety Report, chapter 2 (PPRT); lesson 1-8
6.3 Scope, context and criteriaCustomise the process: define the scope, understand the external and internal contexts, set the risk criteria.lesson 1-5
6.4 Risk assessmentIdentify, analyse, evaluate.lesson 1-6; Safety Report, chapters 3 and 4
6.5 Risk treatmentSelect and implement options, verify their effectiveness, decide whether the residual risk is acceptable.lesson 1-7; Industrial Risks 2, chapter 1
6.6 Monitoring and reviewAssure and improve the quality and effectiveness of design, implementation and outcomes; at all stages.lesson 1-8
6.7 Recording and reportingDocument and report the process and its outcomes for decision making, improvement and dialogue with stakeholders.lesson 1-8; Safety Report, chapter 1

The standard states that the process is “often presented as sequential” but is iterative in practice, and that the variable nature of human behaviour and culture must be taken into account at all stages.

Communication and consultation

Perception and acceptability

Judgement about risk rests on each person’s perception, which can weigh on decisions: a risk judged “acceptable” by the operator may not be so for residents. Consultation serves to make known what is acceptable and why.

Running example: the process applied to Val-des-Pins

  1. Context and criteria : upper-tier Seveso depot (assumption), inhabited surroundings, regulatory and internal criteria (lesson 1-5).
  2. Identification : PHA then HAZOP by line: tank BLEVE, leak at the loading point, overfilling (Safety Report course, chapter 3).
  3. Analysis : probability, intensity, severity (Safety Report course, chapter 4), barrier reliability (Industrial Risks 2 course, chapter 1).
  4. Assessment : compare with the matrix and the tolerated gap (Industrial Risks 2 course, LOPA).
  5. Treatment : add an SIS, a fail-safe valve, an earth mound, reduce the inventory (lesson 1-7).
  6. Monitoring : periodic tests, indicators, audits, lessons learned (lesson 1-8). Recording : safety report, risk register, management reports.

Hands on: the ISO 31000 process